proejct 2 2019-03-06T08:16:21+00:00

Project Description

Project Status:
Construction Completed: November 2013
Construction Start: August 2013
Contract Award: July 2013
Request for Proposals: May 2013

Features
Update to base building to include barrier-free washrooms on each floor
Sustainable design features such as LED lights and sustainable building materials
Floor layouts to maximize natural light
Community Features:
Provides commuter friendly accommodations with male and female change rooms and showers
Co-located MNR staff together into one location.